Construction Contract Advance & Payments (ND 210/2026) API
Minimum and maximum advance, advance guarantee, performance security, warranty, penalty cap and payment schedule with recovery under Decree 210/2026.
Applies Decree 210/2026/NĐ-CP on construction contracts (in force 1 July 2026, replacing Decree 37/2015 and Decree 50/2021): minimum advance by contract type and value (consulting 15 / 20 %, works 10 / 15 / 20 %, supply and EPC 10 %), the 30 % ceiling, the advance guarantee for advances over 1 billion VND, recovery by the time payments reach 80 % of the price, performance security of 2–10 %, the 14-working-day payment deadline and the settlement / liquidation deadlines. Warranty periods and minimum warranty amounts (24 months and 3 % for special and class I works, 12 months and 5 % otherwise) come from Decree 207/2026; the 12 % penalty cap for public investment and PPP from Construction Law 2025 Article 86.
action=schedule (or payments / installments) builds the payment table: accepted value, advance recovered, retention, net payment, cumulative disbursement. late_amount, late_days, late_rate_pct give simple late-payment interest. Contracts signed before 1/7/2026 get the transitional note.
Outside public investment and PPP most terms are agreed by the parties; the public-investment values are then shown as reference. Reference only, not legal advice.
Markdown · OpenAPI · Postman · llms.txt
Parameters
| Name | In | Type | Required | Default | |
|---|---|---|---|---|---|
contract_type | query | string | yes | construction, consulting, supply or epc (EC, EP, PC, EPC, turnkey, other). | |
contract_value | query | number | yes | Contract price at signing, VND (incl. contingency). | |
funding | query | string | no | public | public (public investment / PPP) or other. |
construction_class | query | string | no | special, I, II, III, IV (warranty). | |
advance_pct | query | number | no | Agreed advance %, checked against the minimum and the 30 % ceiling. Also performance_security_pct, retention_pct, recovery_pct. | |
installments | query | number | no | Number of equal payment periods for the schedule, or payments = array of accepted values (VND). | |
contract_date | query | string | no | YYYY-MM-DD; before 2026-07-01 adds the transitional note. | |
late_amount | query | number | no | Late payment amount, with late_days and late_rate_pct (annual %). |
Example
curl "https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4" \
-H "Authorization: Bearer YOUR_API_KEY"const res = await fetch('https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4', {
method: 'GET',
headers: {
Authorization: 'Bearer YOUR_API_KEY',
},
});
const data = await res.json();
console.log(data);import requests
res = requests.get(
"https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4",
headers={"Authorization": "Bearer YOUR_API_KEY"},
timeout=30,
)
print(res.json())<?php
$ch = curl_init('https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4');
curl_setopt_array($ch, [
CURLOPT_RETURNTRANSFER => true,
CURLOPT_HTTPHEADER => ['Authorization: Bearer YOUR_API_KEY'],
]);
$response = curl_exec($ch);
print_r(json_decode($response, true));Response
{
"contract_type": "construction",
"contract_type_vi": "Hợp đồng thi công xây dựng công trình",
"contract_value": 30000000000,
"funding": "public_investment_or_ppp",
"regime": "NĐ 210/2026/NĐ-CP",
"advance": {
"min_pct": 15,
"max_pct": 30,
"rule": "works contract 10–50 tỷ: 15 % (điểm i)",
"chosen_pct": 15,
"amount_vnd": 4500000000,
"guarantee_required": true,
"guarantee": "Advance > 1 tỷ: an advance guarantee of the same value and currency is required before payment; it reduces as the advance is recovered (Điều 12.3.c, d).",
"recovery": "Recovered through the payments; fully recovered when advance + payments for completed work reach 80 % of the contract price (Điều 12.3.m).",
"price_adjustment": "The part of the price matching an advance above the minimum is not price-adjusted from the advance date (Điều 12.3.l)."
},
"performance_security": {
"range_pct": [
2,
10
],
"amount_range_vnd": [
600000000,
3000000000
],
"rule": "2–10 % of the contract price; higher only as allowed by the bidding law; not required in the cases of Luật Đấu thầu Điều 68.2 (Điều 13.2.c, đ).",
"returned": "After all obligations are met or the contractor has moved to the warranty obligation and handed over the warranty security (Điều 13.2.đ)."
},
"warranty": {
"min_period_months": 12,
"min_amount_pct": 5,
"min_amount_vnd": 1500000000,
"rule": "Public funds: warranty ≥ 12 months from acceptance and ≥ 5 % of the contract value, in cash or a bank warranty guarantee (NĐ 207/2026 Điều 32 khoản 2, 5, 7; NĐ 210/2026 Điều 13.2.g, Điều 20).",
"equipment": "Equipment: per contract, not shorter than the manufacturer's warranty (Điều 32 khoản 6)."
},
"penalty": {
"max_pct_of_violated_part": 12,
"rule": "Public investment / PPP: contract penalty ≤ 12 % of the value of the violated part, plus damages as agreed (Luật Xây dựng 2025 Điều 86 khoản 3)."
},
"payment": {
"deadline": "≤ 14 working days after the employer receives a complete valid payment file (Điều 28.4.l); ODA / foreign loans per the treaty (điểm m)",
"late_interest": "Rate agreed in the contract; if not agreed, the overdue rate published by the contractor's bank for each late period (Điều 28.5). See /v1/vn-late-interest."
},
"settlement": {
"settlement_days_max": 60,
"settlement_days_max_large": 120,
"liquidation_days_max": 45,
"liquidation_days_max_large": 90,
"rule": "Settlement ≤ 60 days after completion and acceptance (≤ 120 for large, complex contracts) — Điều 30.3; liquidation ≤ 45 days (≤ 90) — Điều 31.3.b."
},
"schedule": {
"retention_pct": 0,
"recovery_rate_pct": 18.75,
"rows": [
{
"period": 1,
"accepted_vnd": 7500000000,
"advance_recovered_vnd": 1406250000,
"retention_vnd": 0,
"net_payment_vnd": 6093750000,
"cumulative_accepted_vnd": 7500000000,
"advance_outstanding_vnd": 3093750000,
"cumulative_disbursed_pct": 35.3125
},
{
"period": 2,
"accepted_vnd": 7500000000,
"advance_recovered_vnd": 1406250000,
"retention_vnd": 0,
"net_payment_vnd": 6093750000,
"cumulative_accepted_vnd": 15000000000,
"advance_outstanding_vnd": 1687500000,
"cumulative_disbursed_pct": 55.625
},
"…"
],
"fully_recovered": true,
"method": "proportional_80: advance / (80 % × price) of each accepted amount, so the advance is recovered when the accepted (= disbursed) value reaches 80 % (default; interpretation of Điều 12.3.m — unverified)",
"note": "Retention per payment is contractual (agreed_override); amounts exclude price adjustment and VAT."
},
"agreed_override": "Within the legal frame the contract may agree other advance schedules, retention and recovery (Điều 12.2); pass advance_pct, performance_security_pct, retention_pct, recovery_pct.",
"legal": [
{
"ref": "Nghị định 210/2026/NĐ-CP ngày 15/6/2026 quy định chi tiết và hướng dẫn thi hành một số điều của Luật Xây dựng về hợp đồng xây dựng — Điều 12, 13, 20, 28, 30, 31, 33",
"effective_from": "2026-07-01"
},
{
"ref": "Luật Xây dựng số 135/2025/QH15 — Điều 83, 86 (khoản 3: phạt ≤ 12 % với dự án đầu tư công, PPP), 87",
"effective_from": "2026-07-01"
},
"…"
],
"disclaimer": "Reference only, not legal advice; check the official text and the contract.",
"disclaimer_vi": "Thông tin tham khảo, không phải tư vấn pháp lý; hãy đối chiếu văn bản chính thức và hợp đồng.",
"reviewed": "2026-11-16"
}
Use cases
- Check the advance and bonds in a draft works contract
- Generate the payment and advance-recovery table of a contract
- Size the advance guarantee a bank has to issue
- Validate contract terms in project-management software
FAQ
What is the minimum advance for a 30 billion VND works contract?
15 % (works contracts from 10 to 50 billion VND), at most 30 %; above 1 billion VND an advance guarantee of the same value is required (Decree 210/2026 Article 12).
When must the advance be fully recovered?
When the payments, advance included, reach 80 % of the contract price. By default the API recovers advance / (80 % × price) of each accepted amount; recovery_pct overrides it.
How long is the warranty?
For publicly funded works at least 24 months and 3 % for special and class I, 12 months and 5 % for other classes (Decree 207/2026 Article 32).
Related APIs
JSON Validator
Check JSON syntax with exact line and column of errors, and validate data against a JSON Schema (draft 4, 7, 2019-09 or 2020-12).
{ }JSON Formatter
Pretty print JSON with 0-8 spaces or tabs, minify it, or sort object keys recursively. Syntax errors are reported with line and column.
CSVCSV to JSON
Convert CSV into an array of JSON objects using the header row, with delimiter auto-detection, number and boolean typing, and row-level errors.