Vietnam Environmental Permit Checker (EIA, Permit) API

Classify a Vietnamese investment project into environmental group I–IV and get the EIA, environmental permit or registration duty and the competent body.

GETPOSThttps://apibox.io.vn/v1/vn-env-permit

Send the activity type (one of the 28 pollution-risk types of Decree 08/2022 Appendix II, or other) with its capacity, the land / sea area, mining or water licence level, resettlement, public-investment group and yes/no flags for the environmental sensitive factors (urban ward, drinking-water source, protected areas, heritage sites, forest conversion). The API applies Appendices III, IV and V (replaced by Decree 48/2026 from 29/01/2026) and Article 28 of the Law on Environmental Protection, and returns group I, II, III or IV with the rows that triggered it.

For that group it lists the procedures: preliminary EIA (group I), EIA (group I and group II by land / sea / mining / resettlement only), environmental permit (wastewater or dust / gas to be treated, scrap import, hazardous-waste service) or environmental registration at the commune People’s Committee, with the exemption thresholds of Decree 08 Article 32. The appraising and licensing body follows Articles 35 and 41 as amended by Law 146/2025 (Ministry of Agriculture and Environment, provincial chairperson, Defence / Public Security) and the decentralisation of Article 26a. Wastewater flow gives the automatic monitoring duty of Appendix XXVIII.

Sensitive factors are partly qualitative and are answered by you; expansion projects are not modelled. action=activities lists the activity keys, units and capacity bands. Reference only, not legal advice.

Markdown · OpenAPI · Postman · llms.txt

Parameters

NameInTypeRequiredDefault
activitybody|querystringnootherPollution-risk activity key (e.g. metal, seafood, textile_dyeing, livestock; see action=activities) or other.
capacitybody|querynumbernoDesign capacity in the activity unit (t/year, m²/year, MW, l/year, head/day…).
capacity_unitbody|querystringnoAlternative unit when the activity has two (t_yarn_per_year, kwh_per_year).
area_habody|querynumbernoLand / land-with-water area used (ha).
investment_groupbody|querystringnoPublic-investment group: national, A, B, C.
approved_by_na_or_pmbody|querybooleannoInvestment policy decided / approved by the National Assembly or the Prime Minister.
in_industrial_zonebody|querybooleannoLocated in an industrial / economic zone or cluster.
wastewater_m3_daybody|querynumbernoWastewater flow (m³/day); connected_to_central_wwtp=true when piped to a zone plant.
air_emissionsbody|querybooleannoDust / gas emissions that must be treated.
hazardous_waste_kg_monthbody|querynumbernoHazardous waste generated (kg/month); also industrial_solid_waste_kg_month, domestic_waste_kg_day, flue_gas_m3_h.
in_urban_wardbody|querybooleannoSensitive flags: in_urban_ward, discharge_to_drinking_source, protected_area_use, heritage_site_use, protected_land_conversion; plus resettled_people, mountainous.
resource_licencebody|querystringnoMining / water licence level: ministry or province; sea area: sea_area_authority + sea_area_ha.
zone_infrastructurebody|querystringnoindustrial_zone or industrial_cluster for infrastructure projects; provinces = number of provinces spanned.

Example

curl -X POST "https://apibox.io.vn/v1/vn-env-permit" \
  -H "Authorization: Bearer YOUR_API_KEY" \
  -H "Content-Type: application/json" \
  -d '{"activity":"seafood","capacity":5000,"wastewater_m3_day":300}'

Response

{
  "group": "II",
  "group_vi": "Nhóm II",
  "basis": [
    {
      "row": "PL IV STT 1",
      "vi": "Loại hình có nguy cơ gây ô nhiễm, công suất trung bình"
    }
  ],
  "activity": {
    "key": "seafood",
    "vi": "Chế biến thủy sản (trừ chỉ bảo quản)",
    "en": "Seafood processing (except storage only)",
    "risk_level": "III",
    "phu_luc_ii_stt": "16",
    "capacity": 5000,
    "unit": "t_per_year",
    "unit_vi": "tấn sản phẩm/năm",
    "band": "medium",
    "vsic": "1020"
  },
  "procedures": {
    "preliminary_eia": false,
    "eia": false,
    "environmental_permit": true,
    "environmental_registration": false,
    "registration_exempt": false
  },
  "steps": [
    {
      "step": "environmental_permit",
      "vi": "Giấy phép môi trường trước khi vận hành thử nghiệm công trình xử lý chất thải / đi vào vận hành",
      "ref": "Luật BVMT Điều 39, 41, 42 (sửa bởi Luật 146/2025)",
      "authority": {
        "vi": "Chủ tịch UBND cấp tỉnh",
        "en": "Chairperson of the provincial People’s Committee",
        "ref": "Luật BVMT Điều 41 khoản 3 (sửa bởi Luật 146/2025)"
      }
    }
  ],
  "monitoring": {
    "wastewater": "automatic_or_periodic",
    "vi": "Lưu lượng 300 m³/ngày trong khoảng 200 – dưới 500: quan trắc tự động, liên tục hoặc quan trắc định kỳ",
    "ref": "NĐ 08/2022 Điều 97 khoản 2 điểm b; Phụ lục XXVIII STT 2 cột 5"
  },
  "confidence": "medium",
  "reviewed": "2026-11-16",
  "disclaimer": "Reference only, not legal advice; check the official text and the competent authority."
}

Use cases

  • Tell an investor early whether a factory needs an EIA, a permit or only a registration
  • Pre-screen projects in an industrial-zone or consultancy CRM
  • Pick the right appraisal body (ministry or province) before filing
  • Explain the 2026 changes (Law 146/2025, Decree 48/2026) to clients

FAQ

Does every group II project need an EIA?

No. Group II projects classified only by pollution type and capacity go straight to the environmental permit; an EIA is needed for group II only when land / sea use, mining, land conversion or resettlement triggered the group (Law Article 30).

Who decides the sensitive factors?

You answer them as yes/no flags following Decree 08 Article 25(4); the API does not guess locations.

Which texts are applied?

Law 72/2020 as amended by Law 146/2025 (from 1/1/2026), Decree 08/2022 as amended by Decrees 05/2025 and 48/2026, and Circular 02/2022 as amended by Circular 09/2026.