Public Investment Project Group (A, B, C) API

Classify a public investment project as national important, group A, B or C by sector and total investment, with deciding authority and capital period.

GETPOSThttps://apibox.io.vn/v1/vn-project-group

Applies the Public Investment Law 58/2024/QH15 as amended by Law 90/2025/QH15 (consolidated text 96/VBHN-VPQH): national important projects (Article 8: public capital of 30,000 billion VND or more, nuclear plants, conversion of protection / special-use forest, rice land of 500 ha or more, resettlement of 20,000 people in mountains or 50,000 elsewhere, special mechanisms), group A regardless of size (toxic substances and explosives, industrial / high-tech zone infrastructure) and the sector thresholds of Articles 9–11: 4,600 / 240, 3,000 / 160, 2,000 / 120 and 1,600 / 90 billion VND for groups A / B.

The answer gives the group with reasons, the thresholds of the sector, the maximum capital allocation period (A 6 years, B 4, C 3 — Article 57) with extension rules and, with capital_source, the bodies deciding the investment policy and the investment (Articles 18 and 38, after the 2025 two-tier local government reform).

Thresholds can be adjusted by the National Assembly Standing Committee (Article 12). Reference only, not legal advice.

Markdown · OpenAPI · Postman · llms.txt

Parameters

NameInTypeRequiredDefault
sectorquerystringyesSector key (call without parameters for the list), e.g. transport_major, irrigation, urban_infra, health_culture_education, civil_buildings.
total_investment_billionquerynumberyesTotal investment in billion VND (or total_investment in VND).
capital_sourcequerystringnocentral / ministry, provincial, commune or soe for the deciding authority.
resettlement_peoplequerynumbernoPeople resettled (with mountainous=1). Also forest_special_ha, forest_protection_ha, forest_coastal_ha, forest_production_ha, rice_land_ha, nuclear, special_mechanism, toxic_explosive, industrial_zone_infra, public_investment_capital.

Example

curl "https://apibox.io.vn/v1/vn-project-group?sector=transport_major&total_investment_billion=500&capital_source=provincial" \
  -H "Authorization: Bearer YOUR_API_KEY"

Response

{
  "sector": "transport_major",
  "sector_vi": "Giao thông: cầu, cảng biển, cảng sông, sân bay, đường sắt, đường quốc lộ",
  "total_investment": 500000000000,
  "total_investment_billion": 500,
  "group": "B",
  "group_vi": "Dự án nhóm B",
  "reasons": [
    "total investment 500 tỷ from 240 to under 4.600 tỷ (Điều 10 khoản 1)"
  ],
  "thresholds_billion": {
    "group_a_from": 4600,
    "group_b_from": 240,
    "national_public_capital_from": 30000,
    "article": "Điều 9 khoản 2; Điều 10, 11"
  },
  "capital_allocation_period": {
    "max_years": 4,
    "rule": "Điều 57 khoản 2 (counted from the first year capital is allocated to completion; excludes preparation and settlement)",
    "extension": "≤ 1 year by the authority that decided the investment policy (Điều 57.3.b, c)"
  },
  "authority": {
    "investment_policy": "Ủy ban nhân dân cấp tỉnh (Điều 18 khoản 7)",
    "investment_decision": "Chủ tịch UBND cấp tỉnh (Điều 38 khoản 3 điểm c)"
  },
  "related": {
    "construction_law": "Luật Xây dựng 2025 classifies construction projects using the public-investment criteria (Điều 17 — unverified); construction class: /v1/vn-construction-class",
    "environment": "Environmental procedures depend on the project type and scale, not on the group (Luật Bảo vệ môi trường 2020)."
  },
  "note": "Thresholds may be adjusted by the National Assembly Standing Committee (Điều 12). The 2026 amendment of the Public Investment Law reportedly keeps the criteria (unverified).",
  "legal": [
    {
      "ref": "Luật Đầu tư công số 58/2024/QH15 (sửa đổi bởi Luật số 90/2025/QH15), văn bản hợp nhất 96/VBHN-VPQH — Điều 8, 9, 10, 11, 12, 18, 38, 57",
      "effective_from": "2025-01-01"
    },
    {
      "ref": "Nghị định 85/2025/NĐ-CP hướng dẫn Luật Đầu tư công (sửa đổi bởi NĐ 275/2025/NĐ-CP)",
      "effective_from": "2025-04-08",
      "url": "https://vnuf.edu.vn/wp-content/uploads/2025/05/Nghi-dinh_85-2025-ND-CP.pdf"
    }
  ],
  "disclaimer": "Reference only, not legal advice; check the official text.",
  "disclaimer_vi": "Thông tin tham khảo, không phải tư vấn pháp lý; hãy đối chiếu văn bản chính thức.",
  "reviewed": "2026-11-16"
}

Use cases

  • Classify a project before drafting the investment policy proposal
  • Find which body decides the investment policy and the investment
  • Check the capital allocation deadline of a project
  • Tag projects in public-investment management software

FAQ

What is the group B range for roads and bridges?

National highways, bridges, ports, airports and railways: from 240 to under 4,600 billion VND; 4,600 billion and above is group A (Articles 9, 10).

How long can capital be allocated to a group C project?

At most 3 years (A 6, B 4), extendable once by up to 1 year by the body that decided the investment policy (Article 57).

Who decides a group B project funded by a commune?

The commune People's Committee decides the investment policy and its chairperson decides the investment (Articles 18.9 and 38.4).

Related APIs