Construction Contract Advance & Payment Schedule

Minimum and maximum advance, advance guarantee, performance security, warranty, penalty cap and payment schedule with recovery under Decree 210/2026.

Free tool: 20 requests per minute.

Result

Press “Run” to see the result.

Applies Decree 210/2026/NĐ-CP on construction contracts (in force 1 July 2026, replacing Decree 37/2015 and Decree 50/2021): minimum advance by contract type and value (consulting 15 / 20 %, works 10 / 15 / 20 %, supply and EPC 10 %), the 30 % ceiling, the advance guarantee for advances over 1 billion VND, recovery by the time payments reach 80 % of the price, performance security of 2–10 %, the 14-working-day payment deadline and the settlement / liquidation deadlines. Warranty periods and minimum warranty amounts (24 months and 3 % for special and class I works, 12 months and 5 % otherwise) come from Decree 207/2026; the 12 % penalty cap for public investment and PPP from Construction Law 2025 Article 86.

action=schedule (or payments / installments) builds the payment table: accepted value, advance recovered, retention, net payment, cumulative disbursement. late_amount, late_days, late_rate_pct give simple late-payment interest. Contracts signed before 1/7/2026 get the transitional note.

Outside public investment and PPP most terms are agreed by the parties; the public-investment values are then shown as reference. Reference only, not legal advice.

Use this in your code

curl "https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4" \
  -H "Authorization: Bearer YOUR_API_KEY"

API documentation → Get a free API key

FAQ

What is the minimum advance for a 30 billion VND works contract?

15 % (works contracts from 10 to 50 billion VND), at most 30 %; above 1 billion VND an advance guarantee of the same value is required (Decree 210/2026 Article 12).

When must the advance be fully recovered?

When the payments, advance included, reach 80 % of the contract price. By default the API recovers advance / (80 % × price) of each accepted amount; recovery_pct overrides it.

How long is the warranty?

For publicly funded works at least 24 months and 3 % for special and class I, 12 months and 5 % for other classes (Decree 207/2026 Article 32).