Construction Contract Advance & Payment Schedule
Minimum and maximum advance, advance guarantee, performance security, warranty, penalty cap and payment schedule with recovery under Decree 210/2026.
Result
Press “Run” to see the result.
Applies Decree 210/2026/NĐ-CP on construction contracts (in force 1 July 2026, replacing Decree 37/2015 and Decree 50/2021): minimum advance by contract type and value (consulting 15 / 20 %, works 10 / 15 / 20 %, supply and EPC 10 %), the 30 % ceiling, the advance guarantee for advances over 1 billion VND, recovery by the time payments reach 80 % of the price, performance security of 2–10 %, the 14-working-day payment deadline and the settlement / liquidation deadlines. Warranty periods and minimum warranty amounts (24 months and 3 % for special and class I works, 12 months and 5 % otherwise) come from Decree 207/2026; the 12 % penalty cap for public investment and PPP from Construction Law 2025 Article 86.
action=schedule (or payments / installments) builds the payment table: accepted value, advance recovered, retention, net payment, cumulative disbursement. late_amount, late_days, late_rate_pct give simple late-payment interest. Contracts signed before 1/7/2026 get the transitional note.
Outside public investment and PPP most terms are agreed by the parties; the public-investment values are then shown as reference. Reference only, not legal advice.
Use this in your code
curl "https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4" \
-H "Authorization: Bearer YOUR_API_KEY"const res = await fetch('https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4', {
method: 'GET',
headers: {
Authorization: 'Bearer YOUR_API_KEY',
},
});
const data = await res.json();
console.log(data);import requests
res = requests.get(
"https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4",
headers={"Authorization": "Bearer YOUR_API_KEY"},
timeout=30,
)
print(res.json())<?php
$ch = curl_init('https://apibox.io.vn/v1/vn-construction-contract?contract_type=construction&contract_value=30000000000&funding=public&construction_class=II&installments=4');
curl_setopt_array($ch, [
CURLOPT_RETURNTRANSFER => true,
CURLOPT_HTTPHEADER => ['Authorization: Bearer YOUR_API_KEY'],
]);
$response = curl_exec($ch);
print_r(json_decode($response, true));API documentation → Get a free API key
FAQ
What is the minimum advance for a 30 billion VND works contract?
15 % (works contracts from 10 to 50 billion VND), at most 30 %; above 1 billion VND an advance guarantee of the same value is required (Decree 210/2026 Article 12).
When must the advance be fully recovered?
When the payments, advance included, reach 80 % of the contract price. By default the API recovers advance / (80 % × price) of each accepted amount; recovery_pct overrides it.
How long is the warranty?
For publicly funded works at least 24 months and 3 % for special and class I, 12 months and 5 % for other classes (Decree 207/2026 Article 32).