Do I Need a Building Permit in Vietnam?

Is a construction permit needed under the 2025 Construction Law? Exemption clause, start notice, authority, 7-day time limit and dossier list.

Free tool: 20 requests per minute.

Result

Press “Run” to see the result.

A rule engine over Construction Law 135/2025/QH15 (in force 1/7/2026; the permit exemptions of Article 43(2)–(3) since 1/1/2026) and Decree 217/2026/ND-CP. Describe the works with type (house for a detached house, grade_iv, other, or an exempt group such as emergency, temporary, telecom_passive, advertising, public_investment, appraised_project…), work (new, repair, relocate), floors, floor_area (total floor area, m²) and planned_area (true if the site is in a functional / urban-development area of a general plan, a construction area of a commune plan or an area with architecture management regulations).

The response says permit_required (true, false or depends when a fact is missing), the exempting clause (e.g. houses under 7 floors and under 500 m² outside planned areas, Article 43(2)(g); interior repairs without structural change, (h)), whether a start notice must be sent (not for houses of households), the start conditions, and for permits: the authority (commune People's Committee for houses and grade III–IV works), the time limit (7 working days for houses, 10 / 9 for other works, 5 for extension or reissue), online submission, the dossier, the 12-month start window and extensions.

Whether a site lies in a planned area is not in any open dataset: ask the commune People's Committee. The Ministry of Construction notes that most urban houses are inside such areas and still need a permit.

Use this in your code

curl "https://apibox.io.vn/v1/vn-build-permit?type=house&floors=4&floor_area=320&planned_area=true" \
  -H "Authorization: Bearer YOUR_API_KEY"

API documentation → Get a free API key

FAQ

Are all houses under 7 floors exempt now?

No. They are exempt only below 500 m² of floor area and outside the planned / architecture-managed areas listed in Article 43(2)(g); most urban plots are inside such areas.

How long does a house permit take?

7 working days from a complete dossier submitted online (Decree 217/2026, Article 54); extension or reissue 5 working days.

Do households have to notify the start of works?

No. Houses of households and individuals do not send a start notice (Article 43(3), Article 48); other exempt works do.