# Project Management & Consulting Fee (TT 38/2026) API

> Interpolated rates and amounts for project management, feasibility study, design, reviews, tendering and supervision under Appendix VIII of TT 38/2026.

- Endpoint: `GET | POST https://apibox.io.vn/v1/vn-consulting-fee`
- Category: Data & JSON
- HTML docs: https://apibox.io.vn/docs/vn-consulting-fee/ (Vietnamese: https://apibox.io.vn/vi/docs/vn-consulting-fee/)
- Online tool: https://apibox.io.vn/tools/vn-consulting-fee/
- Authentication: `Authorization: Bearer <API key>` or `X-API-Key: <API key>` (free key: https://apibox.io.vn/dashboard/#signup)

Computes the norm rates of Circular 38/2026/TT-BXD, Appendix VIII (in force 1 July 2026): project management (Table 1.1), investment-policy proposal, pre-feasibility and feasibility studies, economic-technical reports (2.1–2.6), design by work type, class and design steps (2.7–2.16, with the 55 % / 60 % shop-drawing share and Table DD1 for equipment-heavy civil works), reviews of studies, design and estimates (2.17–2.20, with minimum fees), tender documents and bid evaluation (2.21–2.23, split 45 / 55 %) and supervision of works, equipment installation and surveys (2.24–2.26).

Rates between two scales use formula (1) of the circular, Nt = Nb − (Nb − Na)/(Ga − Gb) × (Gt − Gb), shown step by step; scales above an open table go by estimate and are returned as null with the reason. Adjustment coefficients (remote / island areas, multi-province, self-managed, equipment ≥ 50 %, renovation, typical design, national important project, equipment ≥ 25 % for estimate reviews) are applied and listed.

All amounts exclude VAT. Tables are imported from the signed PDF and spot-checked; an estimating expert should confirm before use. Reference only.

## Parameters

| Name | In | Type | Required | Default | Description |
|---|---|---|---|---|---|
| `work_type` | query | string | yes |  | `civil`, `industrial`, `transport`, `agriculture` or `infrastructure` (Vietnamese names accepted). |
| `construction_cost` | query | number | yes |  | Construction cost, VND excluding VAT. |
| `equipment_cost` | query | number | no |  | Equipment cost, VND excluding VAT. |
| `construction_class` | query | string | no |  | special, I, II, III, IV (needed for design). |
| `design_steps` | query | number | no | `2` | 2 = shop drawings only, 3 = technical design + shop drawings. |
| `services` | query | string | no |  | Comma list, e.g. project_management,feasibility,design,review_design,review_estimate,bidding_construction,supervision_construction,supervision_equipment. |
| `remote_area` | query | boolean | no |  | Sea, island, land border or extremely difficult commune (PM × 1.35, supervision × 1.2). Also multi_province, self_managed, renovation, typical_design, national_important, k. |
| `approval_date` | query | string | no |  | YYYY-MM-DD; before 2026-07-01 adds the transitional warning. |

## Example request

```bash
curl "https://apibox.io.vn/v1/vn-consulting-fee?work_type=civil&construction_cost=120000000000&equipment_cost=30000000000&construction_class=III&services=project_management,design,supervision_construction" \
  -H "Authorization: Bearer YOUR_API_KEY"
```

## Example response

```json
{
  "work_type": "civil",
  "work_type_vi": "Công trình dân dụng",
  "construction_cost": 120000000000,
  "equipment_cost": 30000000000,
  "construction_class": "III",
  "design_steps": 2,
  "services": [
    {
      "service": "project_management",
      "name_vi": "Chi phí quản lý dự án",
      "name_en": "Project management",
      "table": "Bảng 1.1",
      "base": "construction_cost + equipment_cost",
      "base_vnd": 150000000000,
      "rate_pct": 1.9515,
      "interpolation": "Nt = Nb − (Nb − Na)/(Ga − Gb) × (Gt − Gb) = 2.017 − (2.017 − 1.886)/(200 − 100) × (150 − 100) = 1.9515 %",
      "k": [],
      "amount_vnd": 2927250000,
      "note": "Excludes contingency and the investor's own appraisal costs (Bảng 1.1 notes)."
    },
    {
      "service": "design",
      "name_vi": "Thiết kế xây dựng",
      "name_en": "Construction design",
      "table": "Bảng 2.8",
      "base": "construction_cost",
      "base_vnd": 120000000000,
      "construction_class": "III",
      "rate_pct": 2.214,
      "interpolation": "Nt = Nb − (Nb − Na)/(Ga − Gb) × (Gt − Gb) = 2.25 − (2.25 − 2.07)/(200 − 100) × (120 − 100) = 2.214 %",
      "k": [],
      "amount_vnd": 2656800000,
      "includes": "design documents, cost estimate (12 % of the design cost), technical specifications, maintenance procedure, author supervision, professional liability insurance (mục 3.1, 3.4)"
    },
    "…"
  ],
  "total_vnd": 7726290000,
  "vat": "All rates and amounts exclude VAT.",
  "formula": "Nt = Nb − (Nb − Na)/(Ga − Gb) × (Gt − Gb) (Phụ lục VIII Phần I, công thức (1)); cost = base × Nt × Π k",
  "legal": [
    {
      "ref": "Thông tư 38/2026/TT-BXD ngày 26/6/2026 — Phụ lục VIII Định mức chi phí quản lý dự án và tư vấn xây dựng (Phần I công thức (1); Chương I, II)",
      "effective_from": "2026-07-01",
      "url": "https://datafiles.chinhphu.vn/cpp/files/vbpq/2026/7/38.2026.tt-bxd-pl8dmqldavatvxd_signed1.pdf"
    },
    {
      "ref": "Thông tư 12/2021/TT-BXD Phụ lục VIII (và TT 09/2024, TT 08/2025) — hết hiệu lực từ 01/7/2026",
      "effective_to": "2026-06-30"
    },
    "…"
  ],
  "source": {
    "doc": "Thông tư 38/2026/TT-BXD, Phụ lục VIII — Định mức chi phí quản lý dự án và tư vấn xây dựng",
    "url": "https://datafiles.chinhphu.vn/cpp/files/vbpq/2026/7/38.2026.tt-bxd-pl8dmqldavatvxd_signed1.pdf",
    "sha256": "74738c35c1da28e78cf78903c280efb69d287295c7f88c49b70f75c3d0d9fbbf"
  },
  "unverified": "Rate tables imported automatically from the signed PDF and spot-checked; pending review by an estimating expert.",
  "disclaimer": "Reference only, not legal / estimating advice; check the official text.",
  "disclaimer_vi": "Thông tin tham khảo, không phải tư vấn pháp lý / dự toán; hãy đối chiếu văn bản chính thức.",
  "reviewed": "2026-11-16"
}
```

## Use cases

- Budget consulting costs in a total investment estimate
- Price a design or supervision proposal
- Check a project management unit budget
- Automate cost items in estimating software

## FAQ

### How is a rate between two table columns computed?

By formula (1) of Appendix VIII: Nt = Nb − (Nb − Na)/(Ga − Gb) × (Gt − Gb), with Ga / Gb the upper / lower scales. The answer shows the numbers.

### What base is the design rate applied to?

The construction cost excluding VAT of each work (by type and class). With technical design + shop drawings the shop drawings add 55 % (60 % industrial) of the technical-design rate.

### Which circular applies to projects approved before July 2026?

This API uses TT 38/2026. Projects approved earlier may keep TT 12/2021 under the transitional rules of Decree 206/2026 (not verified); approval_date adds a warning.